Change Costs


The Change Costs tab enables you to display and define information about costs incurred due to changes in the project.

Detail View Header

The field in the top section of this tab defines the data that displays.

Project ID

Identifier of the project currently selected in the grid or that you are defining. This field has a list box. The project description displays to the right of the ID.  

Detail View

The Purchase estimate changes and Other changes screen groups in the bottom section of this tab enable you to display and define information about the costs. Unless otherwise indicated, all fields are optional.

Purchase estimate changes Screen Group Data Table

Information about the changes made to the purchase estimates for the project.

Delete

To delete the entries in the fields to the right, place a check in this field and click Save.

Date

Date the change to the purchase estimate was made.

Estimate ID

Identifier of the purchase estimate that was changed.

Description of change

Description of the change to the purchase estimate.

Cost

Cost of the change to the purchase estimate.

Approved

A check in this field specifies that the purchase estimate change is approved.

User ID

Identifier of the user who changed the purchase estimate. This field has a list box.

Name

Name associated with the User ID. This field is display-only.

Date and time

Date and time the purchase estimate change was approved.

Delay ID

Identifier of the delay that was caused as a result of the change. The Data -> Shop Activity -> Setup -> Work Delay Codes screen defines work delay IDs.

Other changes Screen Group Data Table

The fields in this screen group enable you to display and define administrative or miscellaneous changes associated with charges in the project.

Delete

To delete the entries in the fields to the right, place a check in this field and click Save.

Date

Date the change was made.

Description of change

Description of the change.

Cost

Cost of the change to the purchase estimate.

Approved

If this field has a check, the change was approved.

User ID

Identifier of the user who made the change. This field has a list box.

Name

Name associated with the user ID. This field is display only.

Date and time

Date and time the change was approved.

Delay ID

Identifier of the delay that occurred as a result of the change. The Data -> Shop Activity -> Setup -> Work Delay Codes screen defines work delay IDs.

Delay days

Number of days' progress on the project that was delayed due to the change.