End of Period


The End of Period screen enables you to control the processing required at the end of daily, monthly, and annual periods. You can also reset purchase order, work order, warranty claims, and motor pool reservation numbering.

End-of-period and end of period-monthly processing are tracked. If you attempt to run end of period-monthly for months out of order, a warning message displays.

Detail View Header

System date

Internal system date. It is the same as the organization’s base time zone, which is the time zone in which the application and database servers are located.

Detail View

This section enables you to specify the type of end-of-period processing you want to perform and reset numbering.

End of day

Place a check in this field to run end-of-day processing. The following workflows are included in end-of-day processing:

  1. Reset Part Primary and Part Location

  2. Motorpool Status Updates

  3. Equipment SLA Status

Equipment usage for month ____ Year ____

Place a check in this field to run equipment usage processing, which affects non-pool usage transactions only. You must specify a month (i.e., 1–12) and year (i.e., 1905–2999). The month/year combination must be greater than the month/year combination in the Date last run field and the same as or earlier than the system date.

For each usage transaction recorded during the month, the system calculates the portion of the monthly base rate to charge. The type of apportionment used for each equipment class ID is specified on the Rental Rates tab of the Data -> Equipment Units -> Setup -> Equipment Class -> Primary Information screen.

The month_processed and year_processed columns on the USG_MAIN table are set for motor pool usage tickets posted during the period (base charges are not apportioned to motor pool usage tickets).

If you do not run equipment usage processing for one or more months, calculations are automatically adjusted to recover the base rental charges for the skipped months and the allowances for free meter units per month increased appropriately.

End of month for month ____ Year ____

Place a check in this field to run end-of-month processing.

You must specify a month (i.e., 1–12) and year (i.e., 1905–2999). The month/year combination must be greater than the month/year combination in the Date last run field and the same as or earlier than the system date. It also may not be greater than the month/year combination in the Equipment usage for month ____ year ____ field.

The following workflows are included in end-of-month processing:

Purge obsolete database entries

If this field has a check, obsolete entries are purged. The status of bids, requisitions, and purchase orders is set to CLOSED if all line items are closed. When obsolete entries are purged, the following actions occur:

Retention information for functional areas is specified on the Retention Levels tab of the System Mgmt -> Setup -> Table Management screen. Import start dates and times and whether processing was completed are specified on the Import Data Load tab of the Data -> General Import -> Import screen.

For a list of screens that generate purchase orders, go to Purchasing.

End of year

If this field has a check, end-of-year processing is run. Replacement cost information for each equipment unit in the Equipment Master (EQ_MAIN) table is computed and the year-to-date total business accumulator values in the Vendor (VEN_MAIN) table are reset.

Economic order quantity calculations

If this field has a check, economic order quantity (EOQ) is calculated. EOQ parameters are recalculated for all parts in the Parts Master (PTS_MAIN) table. The calculated order quantity is overridden so that it never exceeds the total number used during the past 12 months. A 30-day lead time for order delivery is assumed if no lead time data are available (because the part was never ordered).

The reorder point, reorder quantity, and safety stock values are calculated as 0 if there has been negative total usage for the part during the previous 12 months.

Capital score calculations for month ____ Year ____

Date last run

The last date on which the specified type of processing occurred.

Month/year last processed

The last month and year that equipment usage and end-of-month processing were completed.

Reset numbering for new year

The Reset numbering for new year button provides access to the PO/Work Order/Warranty Claim Renumbering screen, which enables you to reset purchase order, work order, warranty claim, and motor pool reservation numbering. Ideally, you should complete this step after the close of business in the current year and before the start of business in the new year.